W2 Assignment 2: Project Management
For an organization, a project schedule is given below. Assume that all times are in days.
Task Predecessor Normal Time Crash Time Crash Cost Slope
A None 3 3 NA
B A 2 2 NA
C A 6 2 $600
D A 5 5 NA
E B 3 1 $600
F C 2 2 NA
G D 7 3 $600
H F, G 4 4 NA
I E 5 5 NA
J H 4 4 NA
K I, J 7 7 NA
Draw the activity on node (AON) project network using Microsoft Project or Visio. Perform a critical path analysis for the network and calculate
the earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) times. Calculate the slack time for each activity. Identify the critical path.

Assume that the organization will receive a $1,000 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule.
To maximize the net profit, which task should you crash and by how much?
Submit your answers in a three- to four-page Microsoft Word document.

Answer will be sent by email as attachment.
Other Products from homework:View all products
MGT3059 W2 A3 - Final Project - Production Process
£11.73
MGT3059 W3 A1- Discussion Questions
£10.27
MGT3059 W3 A2 - Dicision Making
£11.00
MGT3059 W3 A3- Final Project - Process Strategy
£10.27
MGT3059 W4 A1 - Discussion Questions
£10.27
MGT3059 W4 A2 -Factory Location Problem
£11.00
MGT3059 W4 A3 - Final Project - Location Strategies
£11.73
MGT3059 W5 A1 - Discussion Questions
£11.00
MGT3059 W5 A3 - Final Project - Layout Strategies
£13.20
MGT3059 W6 A1 - Discussion Questions
£10.27
Last Updated: 5 Oct 2026 00:53:38 PDT home  |  about  |  terms  |  contact
Powered by eCRATER - a free online store builder